South Bluford Drainage and Roadway Improvements
Construction has been completed except for a utility connection on
Columbus Street. Roadway and utility improvement project added a
northbound right-turn lane from Orlando Avenue to Delaware Street,
reconstructed the South Bluford and Orlando Avenue intersection, added
stormwater management facilities, and installed underground water and
sewer utility pipes.
Western Force Main
Under construction; bid awarded October 4, 2016. Sanitary sewer system
intended to take flow off the current SR 50 force main and route it
north along Maguire Road, through the Ocoee downtown area, and on to the
Wastewater Treatment Plant on AD Mims Road. This work has a
relationship with sanitary sewer work now being done as part of Florida
DOT SR 50 road widening project, which is not included in this reporting
mechanism. This project is a key precursor to Ocoee's downtown
redevelopment program.
Bluford Utilities
In design stage. Potable water main being installed and put into
service between Columbus Street and Silver Starr Road, along with a dry
sanitary sewer main that will require completion of the Western Force
Main to put into operation. Some underground piping was installed as
part of the South Bluford Avenue project; design is 90% complete on the
remaining extent. Work should be delayed until the Bluford Street-scape
project’s construction can move forward.
Ocoee Downtown Design Code
Under development. A zoning overlay being developed to provide a more
urban design basis for future downtown Ocoee development. City
Commission is considering a development application moratorium in the
area until the design code is adopted. Expected adoption in Fall 2016.
Bluford Avenue Reconstruction
Under development. A roadway landscaping project intended to address
the appearance of Bluford Avenue from Delaware Street to Silver Star
Road. Construction work cannot proceed until financing has been secured.
In order to leverage utility construction funding, streetscape
installation will have to be part of the restoration phase of the
Bluford Utilities project.
Downtown Redevelopment Plan
The City Commission endorsed
18 capital projects
recommended in the Downtown Redevelopment Plan; formal adoption of the
plan is to be considered at the October 18th City Commission meeting. A
model for guiding private development decisions and public
infrastructure investments in the downtown Ocoee area. This plan
resulted in a list of public infrastructure projects to be included in a
future city bond financing effort. An initial public input hearing, the
Ocoee Downtown Plan Kickoff Meeting
(PDF), was conducted on March 14 at the Lakeshore Center. This event
was broadcast live on Ocoee’s cable TV channel on BrightHouse channel
493. Outreach efforts also included citizen walking tours of the
downtown area, subsequent public meetings, website and social media
campaigns.
Maine Street Extension
Conceptual design completed. Roadway addition that will extend the
present route of Maine Street west from Bluford Avenue to intersect
Maguire Road. Status: Conceptual plan completed and development
agreement is in place to provide required right of way. The transmittal
letter, deed, and temporary construction easement have been drafted to
request transfer of the required ROW. Design phase requires funding,
which has not presently in place. Actual conveyance of ROW by land
owner/developer should wait until roadway design has been completed.
Design and construction cannot proceed until financing has been secured.
The property owner has 30 days to complete the transaction from
receiving certified letter from the city requesting title to the street
ROW.
In addition to these city-funded projects, Ocoee is also
an active participant in the SR 50 road widening project being funded by
the Florida Department of Transportation and the City of Ocoee.