Bluford Avenue Reconstruction

Current Status


The Bluford Avenue Reconstruction Project was awarded to Oelrich Construction, Inc. of Jonesville, FL. Currently Bluford Avenue is closed to all traffic due to construction related activities from North of the Delaware Street / Bluford Avenue intersection to South of the McKey Street / Bluford Avenue intersection. Due to Utility & Stormwater connections that need to be made into McKey Street; the decision has been made to split the currently closed down construction area of Bluford Avenue into (2) Phases: Phase 1 & Phase 2.

Phase 1 work area is defined as the north of the Magnolia Street / Bluford Avenue intersection to the south end of the project at Delaware Avenue. Phase 2 is defined as the northern most project area south of the McKey Street / Bluford Avenue intersection to the north of the Magnolia Street / Bluford Avenue intersection. Bellow is information related to each phase with color coordination with the Phase Map:

  • Phase 1 will be completed and open to all public traffic on Saturday, April 28th, 2018
  • Phase 2 will be shut down and closed to all traffic on Tuesday, May 1st, 2018
  • Phase 3 will be completed and open to all public traffic on Monday, May 14th, 2018
  • Phase 4 will be shut down and closed to all traffic on Monday, June 18th, 2018
  • Phase 2 & Phase 4 (Project Completion) will be completed and open to all public traffic on Saturday, October 6th, 2018

Week of February 26, 2018 – March 2, 2018


Sodding on Lafayette Street is to be placed in the right of way Wednesday of next week but will be completely laid by the end of the work week. The large storm-water structures and piping installation has been completed. The reclaimed water system installation has also been completed. All overall construction sub-grade installations are headed north from Floral Street to Magnolia Street as we prepare for next weeks “Rock & Curb” & “Storm Grates & Sanitary Sewer” installations. Also this week has started the installation of the irrigation sleeves, and lime rock setting and roadway curbing of Bluford Avenue in Phase 1. All of these activities are slated to be completed by the end of this work week. The completion of these activities will begin our march into the finishing of Bluford Avenue in Phase 1.

The Bluford Avenue Reconstruction Project will cost a total of $9,680,000 of which $4,280,000 comes from general bond funds, $2,400,000 comes from the utility bond funds, and $3,000,000 comes from the storm-water utility revenues. The project consists of reconstructing Bluford Avenue from Delaware Street to Silver Star Road concurrent with the installation of water and sanitary sewer utilities, storm-water management, and roadside landscaping. Additionally, $800,000 to have the power lines installed underground.

Bluford Avenue is the central transportation facility for north bound and south bound traffic through the city of Ocoee; extending from Old Winter Garden Road south of Ocoee to Silver Star Road north of Ocoee and through its functional extension as Lakewood Avenue to the SR 429 interchange at Clarcona-Ocoee Road. The intent of the streetscape project is to develop a boulevard appearance, after construction of the utilities and storm-water facilities, that will support adjacent higher density development.

General Fund Capital Bond Construction Schedule


Using the "Construction Manager at Risk" method, the preliminary design should be completed by the time construction funding is available. The project will include a portion of the Downtown Gravity Sewer and the Master Downtown Stormwater system pipeline installation.
BAR Timeline
Legend 2.png
Streetscape1.jpg
Streetscape2.jpg
Streetscape3.jpg